Drupal 9/10 Migration Dashboard
Proposed Drupal Migration Dashboard
This page hosts a Drupal Migration Dashboard with data designed to be most useful for our administration and website owners, managers, and editors.
Updated 3-21-24
Website | Migration Initiated | Content Audit | UX Research (if needed) |
Site Assets Migrated | Custom Modules/ Views | Editors Trained | New Content Creation | Site QA | Site Live |
---|---|---|---|---|---|---|---|---|---|
Accounting and Financial Management | Previously migrated. | N/A | N/A | None | N/A | N/A | N/A | Previously migrated | |
Budget Office | Previously migrated. | Initiated 2-15-23 | N/A | N/A | None | N/A | N/A | N/A | Previously migrated |
Business and Financial Services | 4-4-23 | Initiated 4-4-23. Completed 10-4-23 | N/A | Completed 12-9-23 |
None | 12-15-23 | N/A | Started 12/11/23. Completed 12/19/23 | Live 12-20-23 |
Business Contracts | Previously migrated. | Initiated 10-09-23 | N/A | N/A | None | 4/23 | N/A | N/A | Previously migrated |
Campus Real Estate Office |
01-01-24 |
01-01-24 | N/A | N/A | None | 01-15-24 | N/A | N/A | Live 01-15-24 |
Campus Safety | Decommissioned 8-31-23 | ||||||||
Capital Planning and Construction | Decommissioned 11-16-22 | ||||||||
Central IT Executive Commission | 9-19-22 | Complete 9-23-22 | N/A | Completed 10-4-22 | None | N/A | N/A | Completed | Live 11-30-22 |
Child Development Center | 5-23-23 | Initiated 5-15-23 Completed 10-28-23 | N/A | Completed 10-6-23 | Team Member | Ongoing | N/A | Completed 10-7-23 | Live 1-17-24 |
Commons Event Services | 3-7-23 | Initiated 3-7-23. Complete 4-14-23 | N/A | Completed 4-18-23 | Slideshow Complete | 5-3-23 | Completed 4-14-23 | Completed | Live 5-4-23 |
Document Solutions | 8-23-23 | Initiated 5-15-23 | N/A | Completed 12-15-23 | None | 1-2-24 | N/A | Started 12-15-23 | Live 2-20-24 |
DocuSign | 2-23-23 |
Initiated 12-13-22 Completed 8-11-23 |
N/A | Completed 8-28-23 |
N/A | 3-21-23 | N/A | Completed 10-24-23 | Live 10-25-23 |
Emergency Management | 5-24-23 | Initiated 5-16-23 | N/A | Completed 7-24-23 | N/A | 8-1-23 | Completed 7-24-23 | Completed 7-25-23 | Live 7-28-23 |
Employee Assistance Program (EAP) | 2-22-23 | Initiated 2-22-23. Completed 5-1-23 | Page Tree Testing - In progress, post-launch | Completed 5-9-23 | N/A | N/A | Completed | Live 5-12-23 | |
Enterprise Business Information Technology Solutions (eBITS) | 5-23-23 | Initiated 5-23-23 | N/A | Completed 9-20-23 | N/A | N/A | N/A | Completed 9-21-23 | Live 9-22-23 |
Environmental Health and Safety | 6-6-23 |
Initiated 10-21-22 Completed 10-28-23 |
N/A |
Completed 2-3-24 |
Carousel; Contact List; Sortable List Item (3)
|
2-5-24 | N/A | Ongoing 2-7-24 | Live 2-15-24 |
Facilities Services | 1-30-23 | Initiated 1-30-23 | Initiated Card Sorts and Page Tree Testing 2-24-23 | Completed 10-1-23 | Carousel; Sortable List Item | N/A | Completed 10-1-23 | Completed 10-6-23 | Live 10-9-23 |
FAS Business Services | 6-16-23 | Initiated 5-16-23 Completed 10-4-23 | N/A | Completed 10-9-23 | N/A | N/A | N/A | Completed | Live 10-30-23 |
FAS Communications |
9-14-22 Decommissioned |
Completed 12-5-22 | N/A | Completed 12-5-22 | Custom News Views | Completed 1-31-23 | N/A | Initiated 12-5-22 Completed 1-15-23 | Live 1-20-23 |
Financial and Administrative Services | 3-29-23 | Completed | N/A | Completed 4-24-23 | Sortable Item List - Complete; Homepage Custom Views - Complete. News Views - Complete. | N/A | N/A | Initiated 4-24-23 Completed 6-1-23 | Live 6-2-23 |
Fire Prevention Services | 5-26-23 | Initiated 5-16-23 Completed 10-28-23 | N/A | Completed 12-20-23 | N/A | 1-12-24 | N/A | Completed 1-7-24 | Live 2-22-24 |
HealthPoint Wellness | 6-5-23 | Initiated 2-22-23 Completed 10-28-23 | N/A | Completed 11-3-23 | N/A | 12-15-23 | N/A | Completed 11-16-23 | Live 1-17-24 |
Human Resources | 3-24-23 | Initiated 3-24-23 Completed 10-28-23 | N/A | Completed 11-10-23 | N/A | 10-20-23 | N/A | Completed 11-14-23 | Live 11-27-23 |
Human Resources Support Services | 5-24-23 | Initiated 5-16-23 Completed 10-28-23 | N/A | Completed 10-27-23 | N/A | N/A | Completed 12-21-23 | Live 12-22-23 | |
Historically Underutilized Business/Small Business | 1-24-23 |
Initiated 1-10-23 |
N/A | Completed 7-27-23 | N/A | N/A | N/A | Completed 7-28-23 | Live 7-31-23 |
Lee and Joe Jamail Texas Swimming Center | 9-29-22 | Complete 11-15-22 | N/A | Completed 12-5-22 | N/A | 1-26-23 | N/A |
Begin 12-18-22 |
Live 2-8-23 |
Longhorn Aquatics | 5-25-23 | Initiated 4-27-23 Completed 10-28-23 | N/A | Completed 11-3-23 | Team Member | 1-26-23 | N/A | Completed 11-7-23 | Live 12-6-23 |
Parking and Transportation Services | 5-26-23 | Initiated 5-18-24 Completed 10-28-23 | N/A | Completed 11-10-23 | Team Member | Completed | N/A | Completed 11-15-23 | Live 2-15-24 |
Payroll Services | Previously migrated. | N/A | N/A | N/A | N/A | N/A | N/A | N/A | Previously migrated |
Police Department | 5-25-23 | Initiated 5-17-23 Completed 10-28-23 | N/A | Completed 12-12-23 |
crimefeed
|
Complete 9-29-23 | N/A | Completed 12-15-23 | Live 1-4-24 |
ProCard | 1-24-23 | Initiated 1-10-23 Completed 7-24-23 |
N/A | Completed 7-31-23 | N/A | N/A | N/A | Completed 7-29-23 | Live 7-31-23 |
Procurement and Payment Services | 1-24-23 | Initiated 1-10-23 Completed 7-24-23 |
N/A | Completed 7-31-23 | N/A | N/A | N/A |
Completed 7-31-23 |
Live 8-1-23 |
Planning, Design and Construction (formerly Project Management and Construction Services) | 9-1-23 |
Initiated 9-1-23 |
N/A | Completed 3-3-24 |
Carousel; Division Standard; Division Standard Parent; Division Tech Specs; Flex Image Gallery; Proposal
|
12-13-23 | N/A | Completed 3-21-24 | Live 3-14-24 |
Purchasing Office | Previously migrated. Needs content and UX work. | N/A | Previously migrated | ||||||
Records and Information Management Services | 3-23-23 | Initiated 11-16-22 Completed 8-11-23 | N/A | Completed 8-28-23 | N/A | 3-21-23 | N/A | Completed 10-6-23 | Live 10-10-23 |
Sustainability | 11-16-22 | Initiated 9-21-22 Completed 9-01-23 | Card Sort Testing 7-23 | 10-3-23 | N/A | 8-8-23 | N/A | In Progress 10-8-23 | Live 12-8-23 |
Technology Resources | 6-16-23 | N/A | N/A | 6/26/23 | N/A | 8-4-23 | N/A |
Begin 6-25-23 |
Live 7-10-23 |
Tobacco Free Campus | 10-02-22 | Completed 3-10-23 | N/A | 3-13-23 | N/A | N/A | Completed 3-14-23 | Live 3-16-23 | |
Travel Management Services | 9-29-22 | Completed 12-14-22 | Card Sort (2) Page Tree Testing (1) Complete |
1-7-23 | N/A | 1-15-23 | Ongoing | Completed 1-23-23 | Live 2-8-23 |
UT Learn Homepage | 5-22-23 |
Initiated 5-18-23 |
N/A | 1-3-24 | N/A | N/A | Completed 1-9-24 | Live 2-12-24 | |
UT Works (New Site) | 7-29-22 | N/A | N/A | N/A | N/A | N/A | Completed 10-5-22 | Completed 10-5-22 | Live 10-13-22 |
Utilities & Energy Management | 2-1-23 |
Initiated 2-1-23 |
Card Sort Initiated 2-21-23 | 8-9-23 | N/A | 8-18-23 | N/A | Completed 8-15-23 | Live 8-22-23 |
Workday@UT | 5-22-23 | Initiated 5-18-23 Completed 10-9-23 | N/A | 10-10-23 | N/A | N/A | N/A | Initiated 10-10-23 Completed 10-18-23 |
Live 1-18-24 |